Demolition
Checklist
What you need to do if you are
planning to undertake any demolition work and you are in doubt as
to what you need to do.
- Have you checked to make sure the proposed
demolition is exempt from Planning and Listed Building Consent? See
Conservation Areas and listed buildings.
- Is the proposed building to be demolished exempt from a Section
80 notice?
- Have you included a site plan with the notice that clearly
indicates the building(s) to be demolished?
- Have you sent a copy of your notice to relevant statutory
bodies and adjacent building owners?
- Have you given the local authority six weeks notice prior to
the anticipated demolition starting date?
- Have you received a counter notice from the local
authority?
- Are you familiar with the requirements in the counter notice
regarding making good of adjoining buildings and services etc?
- Is there a likelihood of hazardous materials being encountered
or removed?